Client
USDA Agricultural Research Service
Facility
National Center for Agricultural Utilization Research
Value
$550,000
Performance
Jun – Oct 2017
Delivery
Design-build
Location
Peoria, Illinois

Project overview

SIS removed an existing rooftop unit, its elevated concrete pad and abandoned underground steam piping, then excavated for a grade beam and step footings and erected a steel platform to carry a new unit serving the Building 8 lab.

Scope of work

  • Site, utility and building review
  • Design of foundations and the structural platform
  • SIS design submittals and construction documents
  • Coordination of asbestos abatement on abandoned steam pipe
  • Grade beam and step footing construction
  • Steel platform fabrication and erection
  • Rooftop unit and ductwork installation
  • O&M manual and as-constructed drawings

Challenges and how we solved them

CHALLENGE

Hard deadline to return the lab to service

SOLUTION

When delays hit, the steel platform was fast-tracked through fabrication to recover the schedule.

CHALLENGE

Asbestos-wrapped steam pipes under the pad

SOLUTION

SIS coordinated abatement of the abandoned steam line chase before excavation continued.

CHALLENGE

Footings blocked by vaults and buried utilities

SOLUTION

The footing was re-engineered several times with the structural and geotechnical engineers and the erector, and equipment deliveries were re-sequenced to match.

RESULT

Delivered on time and on budget, as the client required.

For your project

What this project shows

  • Design-build mechanical work in an occupied research laboratory
  • Asbestos discovery handled without missing the deadline
  • Footings re-engineered around buried vaults and utilities
  • Delivered on time and on budget

Learn more

Related capabilities and agencies